In
1996, Caltrans requested that the SWRCB consider adopting
a single NPDES permit for storm water discharges from
all Caltrans properties, facilities, and activities
that would cover the Municipal MS4 requirements as well
as the statewide Construction and Industrial General
Permits requirements. The federal regulations allow
for the issuance of system-wide MS4 NPDES permits. The
permit was adopted in 1999 and is intended to cover
all municipal storm water activities by Caltrans, both
in areas that require an MS4 permit and areas that currently
do not. It is also intended to cover all Caltrans construction
activities that require a permit under the federal regulations.
The
Caltrans MS4 Permit did not change in response
to Phase
II. However, Caltrans projects disturbing an area of
one acre or more must submit a Notice of Construction
to the Regional Board office before the project begins.
|